Musk Asks Suppliers to Move at ‘Light Speed’ on Terafab Plan - Bloomberg

Open the original

Short summary

Elon Musk’s Tesla-SpaceX joint venture, dubbed Terafab, has asked key equipment makers—Applied Materials, Tokyo Electron and Lam Research—for price quotes and delivery timelines on photomasks, etchers, testers and other tools. The team wants to fast-track procurement “at light speed” as it aims to enter advanced chip production.

  • Musk's Tesla-SpaceX venture "Terafab" has requested price quotes and delivery timelines from Applied Materials, Tokyo Electron, and Lam Research for chipmaking equipment (photomasks, etchers, testers, etc.)
  • The team is pushing suppliers to move "at light speed" to compress the typical 5-10 year fab construction timeline
  • Goal is in-house chip production to fix supply bottlenecks for Tesla's self-driving computers and SpaceX's Starlink terminals
  • Major obstacles remain, including securing scarce EUV lithography equipment and matching the years of tool-chain refinement achieved by TSMC and Samsung

Full summary

Elon Musk’s team has quietly started lining up the machinery and materials for “Terafab,” the joint chipmaking venture between Tesla and SpaceX. In recent weeks they’ve asked Applied Materials, Tokyo Electron and Lam Research for price quotes and delivery schedules. The gear list spans photomask writers, silicon substrates, etchers, depositors, wafer cleaners and electrical testers—essential tools for next-generation AI and automotive chips. People familiar with the discussions say Musk’s lieutenants pressed suppliers to move “at light speed.” That sense of urgency reflects Musk’s goal to shortcut the usual five- to ten-year timeline for building a state-of-the-art fabrication plant. He hopes bringing chip production in-house will ease supply bottlenecks for Tesla’s self-driving computers and SpaceX’s Starlink terminals. Insiders caution the project faces steep hurdles. Chip fabs require ultra-clean environments, custom chemical processes and billions in capital investment. Even top-tier foundries like TSMC and Samsung have spent years refining their tool chains and securing reliable sources of photoresist and specialty gases. Musk’s team will need to lock down long lead-time items such as extreme ultraviolet (EUV) lithography gear, which only a handful of companies can supply. Still, Musk’s track record of rapid execution at Tesla Gigafactories and reusable rockets has suppliers bracing for fast turnaround. Quotes and lead-time commitments are expected in the coming weeks. If Terafab can accelerate its build-out without skimping on quality controls, it could reshape how Silicon Valley sources its most critical component.